Progress Report for up to 30 Dec 2022
UNIVERSITY OF BALTISTAN SKARDU
BOUNDARY WALL 
Sr. No. Description Unit Total Quantity Work done Quantity Remaining Quantity Work done %age Net Amount Specified %age of wall's type Amount Paid upto now Paid %age Remarks
1 PreCast Wall (Type-1) Rft 3900 3865.12 34.88 99.1% 21721546 57.72% 17140926.00 78.9%  
2 Chain Link Fence Wall (Type-2) Rft 600 600 0 100.0% 2798917 7.44% 2542271 91%  
3 Solid wall RCC+Block Masonry (Type-3) Rft 1270 1270 0 100.0% 10216859 27.15% 8082623 79.1%  
4 Brbed Wire+Iron Angle wall (Type-4) Rft 8750 7401 1349 84.6% 2892491 7.69% 2216835 77%  
                       
Total Project Cost 37629813 100.00% 29982655.00 80%  
UNIVERSITY OF BALTISTAN SKARDUA1:A1:J13
Progress report for the Month of 15 November to 15 December 2020
Sr. No. Name of Work Administrative Approval T.S Breakup of Cost Pkr. (Million) Starting Date Completion Date Phy. Progress %age upto date Upto date Expenditure Remarks
1 Package 01 Civil Works 1012.938 Million Boundary Wall
1.1 Pre Cast Wall (Type-1) 37     Million 21.72 6/1/2020 11/30/2020 99.1% 78.91% Work Near Completion
1.2 Chainlink Fence Wall (Type-2) 2.80 100.0% 90.83%
1.3 Solid wall RCC+Block Masonry (Type-3) 10.22 100.0% 79.11%
1.4 Barbed Wire+Iron Angle wall (Type-4) 2.89 92% 76.64%
2 Package 02 Building Work 
2.1 Academic Building 522                         Million 324.75 - - - - Lean Concrete has been done of Gate House Building on 27th November 2020.installation of crush plant in progress
2.2 Admin Building 106.01 - - - -
2.3 Main Gate Entrance 81.75 - - 6% -
2.4 External Development 9.50 - - - -
UNIVERSITY OF BALTISTAN SKARDUA1:A1:J13
Progress report for the Month of 15 December 2020 to 15 January2021
Sr. No. Name of Work Administrative Approval T.S Breakup of Cost Pkr. (Million) Starting Date Completion Date Phy. Progress %age upto date Upto date Expenditure Remarks
1 Package 01 Civil Works 1012.938 Million Boundary Wall
1.1 Pre Cast Wall (Type-1) 37     Million 21.72 6/1/2020 11/30/2020 99.1% 78.91% Work Near Completion
1.2 Chainlink Fence Wall (Type-2) 2.80 100.0% 90.83%
1.3 Solid wall RCC+Block Masonry (Type-3) 10.22 100.0% 79.11%
1.4 Barbed Wire+Iron Angle wall (Type-4) 2.89 92% 76.64%
2 Package 02 Building Work 
2.1 Academic Building 522                         Million 324.75 - - - - Wet work (concreting) stoped due to cold winter season.Grading works in progress.
2.2 Admin Building 106.01 - - - -
2.3 Main Gate Entrance 81.75 - - 6% -
2.4 External Development 9.50 - - - -
ESTABLIHMENT UNIVERSITY OF BALTISTAN SKARDU
Progress report upto 30 December 2022
Sr. No. Name of Work Admin Approval T.S Breakup of Cost Pkr. (Million) Tender Cost Breakup of Cost Pkr. (Million) Starting Date Completion Date Phy. Progress %age upto date Upto date Expenditure Million Remarks
1 Package 01 Civil Works 1012.938 Million Boundary Wall
1.1 Pre Cast Wall (Type-1) 37     Million 21.721 37.58     Million 22.02 26/12/2019 30/11/2020 100% 100% 33.648 Work Completed as per Revised B.O.Q Total Amount is 33.829 million
1.2 Chain-link Fence Wall (Type-2) 2.798 3.10 100%
1.3 Solid wall RCC+Block Masonry (Type-3) 10.216 9.56 100%
1.4 Barbed Wire+Iron Angle wall (Type-4) 2.892 2.91 100%
2 Package 02 Building Work 
2.1 Academic Building 01 & 02 600                         Million 331.11 522.83                        Million 280.73 26-10-2020 26-10-2022 75% 73% 206.955 Work in Progress
2.2 Admin Building 114.61 99.42 85%
2.3 Main Gate Entrance 92.60 79.33 40%
2.4 External Development 61.00 63.36 90%
3 Package-03 Building Work
3.1 Main Library 445  Million 91.837 399.72 Million 81.87 10/6/2021 10/6/2023 5% 22% 11.414 Work in Progress
3.2 Boys Hostel 165.766 147.93 8%
3.3 Bachelor Hostel 55.735 49.67 15%
3.4 Infrastructure/External Development 131.446 120.25 60%
STRENGTHENING UNIVERSITY OF BALTISTAN SKARDU
Progress report upto 30 of December 2022
Sr. No. Name of Work Admin Approval T.S Breakup of Cost Pkr. (Million) Tender Cost Breakup of Cost Pkr. (Million) Starting Date Completion Date Phy. Progress %age upto date Upto date Expenditure Million Remarks
1 Phase -I Civil Works 595.482 Million Construction of Balti Museum (02 Unit) and Girls Hostel i/c B.W and Guard Room
1.1 Balti Museum (02 Unit) 226     Million 59.423 212.327    Million 56.293 1/16/2022 1/16/2024 7% 7% 64.875 Work in Progress
1.2 Girls Hostel i/c B.W and Guard Room 166.354 156.034 12%
2 Phase-II Construction of 04 Incubation Center in 04 District of Baltistan Region
2.1 Incubation Center Distrct Skaradu   115                      Million 40.00               Consultant Hired and Tender Documents Completed Tender Advertisment will be finalized acording to expected Release
2.2 Incubation Center Distrct Shigar 25.00    
2.3 Incubation Center Distrct Ghanchee 25.00    
2.4 Incubation Center Distrct Kharmang 25.00