Progress Report for up to 30 Dec 2022
- Boundary Wall
- 15 November to 15 December 2020
- 15 December 2020 to 15 January 2021
- Upto 30 December 2022
- Strengthening University of Baltistan Skardu
UNIVERSITY OF BALTISTAN SKARDU | |||||||||||
BOUNDARY WALL | |||||||||||
Sr. No. | Description | Unit | Total Quantity | Work done Quantity | Remaining Quantity | Work done %age | Net Amount | Specified %age of wall's type | Amount Paid upto now | Paid %age | Remarks |
1 | PreCast Wall (Type-1) | Rft | 3900 | 3865.12 | 34.88 | 99.1% | 21721546 | 57.72% | 17140926.00 | 78.9% | |
2 | Chain Link Fence Wall (Type-2) | Rft | 600 | 600 | 0 | 100.0% | 2798917 | 7.44% | 2542271 | 91% | |
3 | Solid wall RCC+Block Masonry (Type-3) | Rft | 1270 | 1270 | 0 | 100.0% | 10216859 | 27.15% | 8082623 | 79.1% | |
4 | Brbed Wire+Iron Angle wall (Type-4) | Rft | 8750 | 7401 | 1349 | 84.6% | 2892491 | 7.69% | 2216835 | 77% | |
Total Project Cost | 37629813 | 100.00% | 29982655.00 | 80% |
UNIVERSITY OF BALTISTAN SKARDUA1:A1:J13 | |||||||||
Progress report for the Month of 15 November to 15 December 2020 | |||||||||
Sr. No. | Name of Work | Administrative Approval | T.S | Breakup of Cost Pkr. (Million) | Starting Date | Completion Date | Phy. Progress %age upto date | Upto date Expenditure | Remarks |
1 | Package 01 | Civil Works 1012.938 Million | Boundary Wall | ||||||
1.1 | Pre Cast Wall (Type-1) | 37 Million | 21.72 | 6/1/2020 | 11/30/2020 | 99.1% | 78.91% | Work Near Completion | |
1.2 | Chainlink Fence Wall (Type-2) | 2.80 | 100.0% | 90.83% | |||||
1.3 | Solid wall RCC+Block Masonry (Type-3) | 10.22 | 100.0% | 79.11% | |||||
1.4 | Barbed Wire+Iron Angle wall (Type-4) | 2.89 | 92% | 76.64% | |||||
2 | Package 02 | Building Work | |||||||
2.1 | Academic Building | 522 Million | 324.75 | - | - | - | - | Lean Concrete has been done of Gate House Building on 27th November 2020.installation of crush plant in progress | |
2.2 | Admin Building | 106.01 | - | - | - | - | |||
2.3 | Main Gate Entrance | 81.75 | - | - | 6% | - | |||
2.4 | External Development | 9.50 | - | - | - | - |
UNIVERSITY OF BALTISTAN SKARDUA1:A1:J13 | |||||||||
Progress report for the Month of 15 December 2020 to 15 January2021 | |||||||||
Sr. No. | Name of Work | Administrative Approval | T.S | Breakup of Cost Pkr. (Million) | Starting Date | Completion Date | Phy. Progress %age upto date | Upto date Expenditure | Remarks |
1 | Package 01 | Civil Works 1012.938 Million | Boundary Wall | ||||||
1.1 | Pre Cast Wall (Type-1) | 37 Million | 21.72 | 6/1/2020 | 11/30/2020 | 99.1% | 78.91% | Work Near Completion | |
1.2 | Chainlink Fence Wall (Type-2) | 2.80 | 100.0% | 90.83% | |||||
1.3 | Solid wall RCC+Block Masonry (Type-3) | 10.22 | 100.0% | 79.11% | |||||
1.4 | Barbed Wire+Iron Angle wall (Type-4) | 2.89 | 92% | 76.64% | |||||
2 | Package 02 | Building Work | |||||||
2.1 | Academic Building | 522 Million | 324.75 | - | - | - | - | Wet work (concreting) stoped due to cold winter season.Grading works in progress. | |
2.2 | Admin Building | 106.01 | - | - | - | - | |||
2.3 | Main Gate Entrance | 81.75 | - | - | 6% | - | |||
2.4 | External Development | 9.50 | - | - | - | - |
ESTABLIHMENT UNIVERSITY OF BALTISTAN SKARDU | ||||||||||||
Progress report upto 30 December 2022 | ||||||||||||
Sr. No. | Name of Work | Admin Approval | T.S | Breakup of Cost Pkr. (Million) | Tender Cost | Breakup of Cost Pkr. (Million) | Starting Date | Completion Date | Phy. Progress %age upto date | Upto date Expenditure Million | Remarks | |
1 | Package 01 | Civil Works 1012.938 Million | Boundary Wall | |||||||||
1.1 | Pre Cast Wall (Type-1) | 37 Million | 21.721 | 37.58 Million | 22.02 | 26/12/2019 | 30/11/2020 | 100% | 100% | 33.648 | Work Completed as per Revised B.O.Q Total Amount is 33.829 million | |
1.2 | Chain-link Fence Wall (Type-2) | 2.798 | 3.10 | 100% | ||||||||
1.3 | Solid wall RCC+Block Masonry (Type-3) | 10.216 | 9.56 | 100% | ||||||||
1.4 | Barbed Wire+Iron Angle wall (Type-4) | 2.892 | 2.91 | 100% | ||||||||
2 | Package 02 | Building Work | ||||||||||
2.1 | Academic Building 01 & 02 | 600 Million | 331.11 | 522.83 Million | 280.73 | 26-10-2020 | 26-10-2022 | 75% | 73% | 206.955 | Work in Progress | |
2.2 | Admin Building | 114.61 | 99.42 | 85% | ||||||||
2.3 | Main Gate Entrance | 92.60 | 79.33 | 40% | ||||||||
2.4 | External Development | 61.00 | 63.36 | 90% | ||||||||
3 | Package-03 | Building Work | ||||||||||
3.1 | Main Library | 445 Million | 91.837 | 399.72 Million | 81.87 | 10/6/2021 | 10/6/2023 | 5% | 22% | 11.414 | Work in Progress | |
3.2 | Boys Hostel | 165.766 | 147.93 | 8% | ||||||||
3.3 | Bachelor Hostel | 55.735 | 49.67 | 15% | ||||||||
3.4 | Infrastructure/External Development | 131.446 | 120.25 | 60% |
STRENGTHENING UNIVERSITY OF BALTISTAN SKARDU | ||||||||||||
Progress report upto 30 of December 2022 | ||||||||||||
Sr. No. | Name of Work | Admin Approval | T.S | Breakup of Cost Pkr. (Million) | Tender Cost | Breakup of Cost Pkr. (Million) | Starting Date | Completion Date | Phy. Progress %age upto date | Upto date Expenditure Million | Remarks | |
1 | Phase -I | Civil Works 595.482 Million | Construction of Balti Museum (02 Unit) and Girls Hostel i/c B.W and Guard Room | |||||||||
1.1 | Balti Museum (02 Unit) | 226 Million | 59.423 | 212.327 Million | 56.293 | 1/16/2022 | 1/16/2024 | 7% | 7% | 64.875 | Work in Progress | |
1.2 | Girls Hostel i/c B.W and Guard Room | 166.354 | 156.034 | 12% | ||||||||
2 | Phase-II | Construction of 04 Incubation Center in 04 District of Baltistan Region | ||||||||||
2.1 | Incubation Center Distrct Skaradu | 115 Million | 40.00 | Consultant Hired and Tender Documents Completed Tender Advertisment will be finalized acording to expected Release | ||||||||
2.2 | Incubation Center Distrct Shigar | 25.00 | ||||||||||
2.3 | Incubation Center Distrct Ghanchee | 25.00 | ||||||||||
2.4 | Incubation Center Distrct Kharmang | 25.00 |